Subject: Conoco/TW at Monument--- level "A" +/- 30% cost estimate
Cc: kevin.hyatt@enron.com, morgan.gottsponer@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: kevin.hyatt@enron.com, morgan.gottsponer@enron.com
X-From: Abdmoulaie, Mansoor </O=ENRON/OU=NA/CN=RECIPIENTS/CN=NOTESADDR/CN=41680A35-823F91BA-862566E1-503199>
X-To: Lokay, Michelle </O=ENRON/OU=NA/CN=RECIPIENTS/CN=MLOKAY>
X-cc: Hyatt, Kevin </O=ENRON/OU=NA/CN=RECIPIENTS/CN=KHYATT>, Gottsponer, Morgan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=MGOTTSP>
X-bcc: 
X-Folder: \MLOKAY (Non-Privileged)\TW-Commercial Group
X-Origin: Lokay-M
X-FileName: MLOKAY (Non-Privileged).pst

Design volume=60 mmcf/d at 700 psig

The following is a summary of  facility requirements and the associated cots to tie Conoco to TW-10" suction side of the Monument Compressor Station.

Facilities					A-release Costs($) 

10X8" Tee & side valve				30,000

EFM, DAS,RTU, Chromatograh			130,000
and H2o Analyzer and buildings.  

8"-Ultrasonic measurements			40,000

Flow control valve with pressure override	135,000
and Isolation valve

Overhead 15%					50,250
Contingency 10%				33,500

Total						$418,750										
		 


If you have any questions please call.